Check out our popular new TED Talk.

Construction worker operates a crane, lifting large cable spools from a flatbed truck on a clear day.

Salt River Project (SRP).

8.5 MI
230KV
RECONDUCTORING
SRP Orme Rudd Project

Project overview.

Salt River Project (SRP) completed an 8.5-mile reconductoring project on their double-circuit 230kV transmission line between the Orme and Rudd substations in Phoenix, Arizona, in May 2024. The project aimed to increase capacity from 2,210A continuous/2,382A emergency to at least 3,800A continuous/4,180A emergency to accommodate regional load growth.

Technology.

After evaluating proposals from several HTLS manufacturers through a formal RFP process, SRP selected TS Conductor's double-bundled TS Cloudveil M3 (1181 kcmil) as the optimal solution, replacing the existing double bundle 954 Rail ACSR configuration. The evaluation included technical specifications, cost, schedule, and extensive testing (including vibration and full tension compression testing).

Challenges.

SRP needed to significantly increase line capacity while preserving their existing structures, which still had approximately 50 years of useful life remaining (having been installed in the 1970s). Traditional ACSS-based reconductoring options would have required replacing most or all structures due to excessive thermal sag at higher operating temperatures, despite meeting ampacity requirements. The project also required completion within an aggressive 18-month timeline from design to energization.

Key outcomes.

TS Conductor's compatibility with standard installation practices was a key factor in the project's success. SRP crews seamlessly adapted to the new technology without any specialized training or equipment required, keeping the project on track and maintaining high safety standards throughout.

Tall utility poles with multiple power lines stretch into the distance against a blue sky.
INCREASED AMPACITY

Increased the line's ampacity from 2,210A to 3,978A at normal operating conditions, and emergency capacity from 2,382A to 4,250 — exceeding the target requirements.

NO MODIFICATIONS REQUIRED

Maintained a similar outer diameter (increasing only slightly from 1.165" to 1.17") with minimal tension and thermal sag, allowing use of existing structures without modifications.

COMPLETED UNDER BUDGET, IN LESS TIME

Completed ahead of schedule, with final costs totaling approximately $10.1 million, under the initial budget of $11.5 million.

HARDWARE SOLUTION

SRP partnered with AFL for hardware, including suspension assemblies, compression presses, vibration dampers, and compression sleeves. The team optimized pulling sections and minimized conductor waste through custom reel lengths.

More details.

Conductor Comparison

View PDF

Public Planning

View PDF

Darcy Partners Presentation

View PDF

More case studies.