Florida Power and Light - Eldora-Finca-Heritage

Florida Power and Light (FPL).

5 MI
230KV
REBUILD
Florida Power and Light - Eldora-Finca-Heritage

Project overview.

Florida Power & Light (FPL) completed a 5-mile rebuild of their 230kV Eldora-Finca-Heritage transmission line in Q2 2024. The project aimed to upgrade the existing 954 ACSR/AW conductor with a capacity of 1495 Amps to meet a new capacity requirement of 3000 Amps.

Technology.

FPL compared the TS Williamson M3 10 (2093 kcmil) conductor with the 1926 ACSS Cumberland, ultimately selecting the TS solution.

Challenges.

This rebuild presented unique challenges due to its location in a water management right-of-way (ROW). Specific easement requirements to ensure access to the waterway for maintenance meant that tower locations and ruling spans were fixed and pre-determined, limiting FPL's design flexibility.

Key outcomes.

TS Williamson reduced thermal sag by over 7' compared to ACSS at maximum operating temperature. This allowed FPL to use smaller, simpler 120', 32 kip single-piece structures instead of the 140', 45 kip two-piece structures required for ACSS. TS Conductor's compatibility with standard installation practices and equipment helped ensure worker safety and keep the project on schedule and within budget.

Florida Power and Light - Eldora-Finca-Heritage
INCREASED AMPACITY

Increased capacity from 1,495 Amps to 3,198 Amps, surpassing the original 3,000 Amp requirement.

LOWER CAPEX

Reduced total structure and conductor costs by over $2.5 million compared to the ACSS option.

FUTURE PROOF

Met unique ROW constraints while providing additional capacity for future flexibility

More details.

Conductor Comparison

View PDF

CapEx Savings Analysis

View PDF